About this project
Chestnut Row broke ground in October 2018 and delivered in May 2020 — eight weeks into the pandemic. We held the schedule by converting the ground floor to flexible live/work bays mid-construction, and the building leased to 92% within twelve months. It anchors a streetscape the Highland neighborhood had planned for since 2009.
Highlights
- Delivered May 2020, on budget, eight weeks into the pandemic
- Ground floor converted mid-build to 11 flexible live/work bays
- 92% leased within twelve months of opening
- Named 2021 Multifamily Project of the Year by NAIOP Colorado
Construction timeline — Chestnut Row
Scrub from land acquisition to ribbon cutting.

April 2017Complete
Land acquisition · April 2017
Kestrel & Pike acquires a full Highland block — a former lumber yard and two houses — completing assembly in December 2017.